Shoreditch Village, Phase II site progress

 

Shoreditch Village, Phase II: our project with AHMM for Brockton Capital is progressing fast on site.

The basement dig is underway and is formed by a mixture of underpinning and contiguous piling. Hydraulic flying props and buttress piles are now in position, providing temporary restraint to the basement walls until the ground floor slab is cast. The steel frame is due to start on site this autumn.

The existing site includes the remains of a medieval friary and church. HTS is working closely with Historic England to minimise disruption to the archaeological works on site.

When complete the project will create two new flexible office and retail buildings with a glazed connection.

 